After another round of delays, Intel's Licking County project timeline now appears to be at odds with promises the company ...
Intel’s massive computer chip factory, originally scheduled to open this year, has been delayed again, this time to the next ...
Intel Corp. is slowing down construction of its Ohio complex again, with the semiconductor maker now saying the fabs will ...
COLUMBUS, Ohio -- Intel’s massive semiconductor project in central Ohio has been delayed, again. On Friday, the company ...
The site in New Albany, Ohio, is now set to be completed in 2030, with operations starting as late as 2031, compared with the ...
The chip manufacturer said it had invested $3.7 billion through last year, and is committed to spending another $3.2 billion ...
Intel’s plans to build two chip factories in New Albany, Ohio for an investment of more than $28 billion have been postponed.
Intel, the financially embattled chipmaker, has delayed the opening of its first Ohio factory to 2030 or 2031, multiple years after it was to open.
The first phase of the facility, known as Mod 1, should be finished in 2030, with chip production beginning between 2030 and ...
Intel originally said it expected to begin production at the New Albany, Ohio, site in 2025, and later pushed that back to ...
Intel has already poured more than 200,000 cubic yards of concrete and more than 20 cranes are currently operating at the site, where the ... to help with the construction of each factory completed by ...