Intel’s plans to build two chip factories in New Albany, Ohio for an investment of more than $28 billion have been postponed.
Intel Corp. is slowing down construction of its Ohio complex again, with the semiconductor maker now saying the fabs will ...
The project, which was slated to begin operations in 2026, is underway to meet surging demand for advanced semiconductors.
COLUMBUS, Ohio -- Intel’s massive semiconductor project in central Ohio has been delayed, again. On Friday, the company ...
The first phase of the facility, known as Mod 1, should be finished in 2030, with chip production beginning between 2030 and ...
Key TakeawaysIntel said it plans to push back the opening of two chipmaking facilities currently under construction in ...
Jeff Gottke and Barrett Thomas said Knox and Richland counties have opportunities to contribute to Tier 2 or 3 of the Intel supply chain.
When Intel broke ground less than three years ago, the chipmaker said it could be online by 2025, but that goal for the Ohio ...
Intel filed its latest progress report with the state of Ohio on Friday. Here's what it shows about the again delayed chip factories.
Intel originally said it expected to begin production at the New Albany, Ohio, site in 2025, and later pushed that back to ...
Intel has revised the construction schedule for its Ohio One semiconductor manufacturing site in New Albany, Licking County, ...
Intel is delaying the opening of its $28 billion Ohio chip plants yet again. In an update on Friday, Intel executive vice ...